Tower crane disassembly steps

After the tower crane use, often it means the main part of the building was completed, entered the phase of interior decoration. However, this period is often high incidence of accidents. Therefore, our technical personnel in accordance with relevant experience, summed up the steps.
Hoping to help the majority of crane practitioners.
1.down hooks, remove the hoisting rope fixed end, roll back the rope.
2.lifting the car back to the boom heel fixed, luffing rope reel back, remove the cable luffing mechanism.
3. Remove the three counterweight.
4. Removal boom.
5. Remove the last piece of counterweight.
6. Remove the balance arm.
7.disassemble cab.
8.dismantle the tower.
9. turntable fixing section and the rotation mechanism demolition.
10. the removed section and rotary turntable fixing mechanism.
11. removal of the tower: according to the program set up opposite the tower dismantled tower.
12.demolition crane chassis.
13.after the removal of tower crane parts required to break down and decompose transported from the scene.